Planning Application

If the application has not been determined you can use the Yellow 'Comment on Application' button to make representations.

For information click links below:

Plans, documents and other information that forms part of the application is attached at the bottom of the page.


Application Details
Reference number FUL/2020/1476 Application Description Full Planning Application (Major)
Coventry Reference
Site Address Land south of Coventry National Grid Substation
Parrotts Grove
Alderman's Green
Coventry
CV2 1NQ
Proposal Construction and operation of a 49.9 MW battery storage facility, fencing and site access road on land to the south of the Coventry National Grid Substation, Parrotts Grove, Alderman's Green, Coventry.
Application Status FAPP
Received Date 29/06/2020 Valid date 02/07/2020 Decision expected Date 01/10/2020
Case Officer Liam D'Onofrio
End of Public Consultation Period 13/08/2020
Referred to Secretary of State
Decision level Delegated Committee Date
Decision APPROVED Decision Date 22/01/2021
Temp Permission Expiry Date Permission Expiry Date 22/01/2024
Agent Name
WYG
Images
Site Area Plan
Layout Plan
Layout Plan 1
EARTHING TRANSFORMER ARRANGEMENT Dwg:TSC54-G010
FEEDER PILLAR ARRANGEMENT Dwg:TSC54-Coventry-GA-G009
AUXILIARY TRANSFORMER ARRANGEMENT Dwg:TSC54-Coventry-GA-G008
33kV SWITCHGEAR UNIT 2 ARRANGEMENT Dwg:TSC54-Coventry-GA-G007
33kV SWITCHGEAR UNIT 1 ARRANGEMENT Dwg:TSC54-Coventry-GA-G007
Fencing Dwg:TSC54-Coventry-GA-G006
Dwg:TSC54-Coventry-GA-G005
Dwg:TSC54-Coventry-GA-G004
Dwg:TSC54-Coventry-GA-G003
Dwg:TSC54-Coventry-GA-G002
Dwg:TSC54-Coventry-GA-G001
Dwg:TSC54-Coventry-GA-E001
Pivot Coventry Battery Site FRA First Issue_Part2
Pivot Coventry Battery Site FRA First Issue_Part1
Calculations
DESIGN AND ACCESS STATEMENT
Coventry Cover Letter
Dwg:COV003
Dwg:COV002
Dwg:COV001
Summary
Application Form
Coventry SS_DTS Rpt_V2 Issue reduced 25.6.20_Part4
Coventry SS_DTS Rpt_V2 Issue reduced 25.6.20_Part3
Coventry SS_DTS Rpt_V2 Issue reduced 25.6.20_Part2
Coventry SS_DTS Rpt_V2 Issue reduced 25.6.20_Part1
Access and Transport
Ecology Coventry Substation_FINAL_ISSUE v2
A110984 Coventry Substation Ecological Appraisal
A110984 Coventry Landscape Visual Statement v3
Noise A1 Pivot Power Coventry 12Jun2020
Consultation Response - Health & Safety 14.07.2020
Consultation Response -Economic Development Service - 22.07.2020
Consultation Response - Canal River Trust 03.08.2020
Consultation Response EP 06.08.2020
Consultation Response - Bedworth & Nuneaton Council 12.08.2020
Returned Neighbour Letter
Landscape Proposals Dwg: 05 Rev A
Consultation Response - Ecology 01.10.2020
Consultation Response EP 11.11.2020
Consultation Response -Ecology Bio diversity offset - 16.11.2020
Consultation Response - Economic Development 24.11.2020
Officer report
Decision notice
S106 Agreement.
Technical Response - Noise
Swept Path Analysis DWG:SPA01 Rev C
Consultation Response - Highways - 29.10.2020

Print this page